Timeline of Events

  • April 16th, 2013 Writ was dropped for the election and on May 14th, 2013 Election called.
  • February 2013 - Ministry of Education requested that the VSB complete a Value Analysis of the preferred option. (The Value Analysis is completed after the election and results in no cost savings.)
  • October 2012 - Ministry of Education requested the scope of the project be limited to seismic upgrade only. Boiler removed from plan and the project is now at $29 million.
  • October 17, 2011 - VBE Board Meeting recommends the Preferred Definition report and submits it to the Ministry of Education.This was the timeline.
  • June 2011 - Open House and community feedback
  • December 6, 2010 - Capital Project Bylaw passed
  • December 2-3, 2009 - Community Display and community feedback
  • April 20, 2009 - Lord Strathcona Visioning Session with all stakeholders

For more information, visit: http://www.vsb.bc.ca/strathcona-renewal

"It seems that Strathcona is continually treated as a ghetto and that it's residents are not worth consideration although we pay taxes, just like everyone else."

3 Ways to Help Make Strathcona Elementary Safe

Sign the Petition
Join Failed to get data. concerned parents

Send an email

Tweet!

Send an Email

This form will send your message to: Mike DeJong MLA (Minister of Finance), Peter Fassbender MLA (Minister of Education), Sam Sullivan MLA (Vancouver-False Creek), and Jenny Kwan MLA (Vancouver East). Use the default text, or even better, in your own words.